1. Start
Start Date agreed upon with 25% of payment received

2. Week1-2 -- Initial Set Up
Client
Develops site map and gathers all information that will be presented on the site including pictures, text, videos and audio files
dreamSD
Develops design scheme(s) and submits them to the client for approval and finalizes
at the end of the two weeks

3. Week 2-6 -- Content Input
Client
Allowed to make minor changes to the overall content and design as dreamSD updates on the progress
dreamSD
Inputs all content information into the design scheme according to the site map

4. Week 6 -- Site Launch
The site is launched at the beginning of the sixth week per client approval once complete payment is received.

5. Week 6-8 -- Update
Minor updates and changes are made to the site per clients request for no additional charge up to 10 hours of work for two weeks, with no more than 5 hours per week; each additional hour will be subject to the approved hourly update agreement.

CONTACT

General Information
info@dreamsd.com
303.817.6295

Nathan Headley - Design, Sales, President
nheadley@dreamsd.com

Dan Collins - Design, Site Management
dcollins@dreamsd.com

   
Copyright 2008 dreamSD Group All rights reserved